GIS’s flagship renewable energy project, solar power for Orange Cameroon’s Technical Directorate in Makepe (Douala) combines two types of installation: ground-mounted photovoltaic arrays along the site fences, and solar carports that shade the car park while generating electricity.
Our teams handled the civil works: reinforced concrete ground beams for the ground-mounted arrays, anchor blocks cast around templates to set the bolts in exactly the right place, and compaction and reinstatement of the car park paving. The galvanised steel structures were then assembled and the panels installed, with strict use of PPE and work-at-height procedures.
Carried out on an operating site, this project shows our approach to solar: one team for foundations, structures and installation, with permanent site marking for the safety of staff and users.
Scope
- Setting-out and earthworks
- Reinforced concrete ground beams for ground-mounted arrays
- Reinforced concrete blocks with templates and anchor bolts
- Compaction and reinstatement of car park paving
- Assembly of galvanised steel structures
- Photovoltaic carports
- Installation of photovoltaic panels
- Masonry partitions for the technical room